Upgrade Runway, Taxiway and airplane Parking in KKIA

Project Information

Client: General Authority of Civil Aviation
Location: Riyadh
Starting Date: July - 2015
Completion Date: January - 2018
Contract Value: SAR 376,761,184
Contract Value: USD 100,469,648
Scope of work: Civil, Electrical and Mechanical
Project Manger: Samer Beyrouthy

Project Brief

Construction of one new flexible pavement (asphalt) taxiway with complete AGL / electrical and mechanical works: - Taxiway GP of 1,400m x 60m

Refurbishment and upgrade of existing taxiways G, E and T including all civil, AGL and electrical works.

Construction of a new storm drainage line with culverts and crossings.

Extension of existing cargo apron with complete AGL / electrical, mechanical and fuel hydrant system.

Relocation of the airport's main fuel supply line (approximately 11,500lm of 24" fuel lines with 350lm of 12" and 16" branches).

Replacing the airport's existing airfield lighting "control system" with a complete new "Control & Monitoring System" (ALCMS).

Resurfacing of Primary and Secondary Runways (touch down zones).