Upgrade Runway, Taxiway and airplane Parking in KKIA

Project Information

Client: General Authority of Civil Aviation
Location: Riyadh
Starting Date: December - 2014
Completion Date: June - 2016
Contract Value: SAR 396,597,952
Contract Value: USD 105,759,456
Scope of work: Civil, Electrical and Mechanical
Project Manger: Samer Beyrouthy

Project Brief

Construction of three new flexible pavement (asphalt) taxiways with complete AGL / electrical and mechanical works: - Taxiway GP of 4,300m x 50m

  • Taxiway T2 of 600m x 50m
  • Taxiway W of 125m x 50m

Refurbishment and upgrade of existing taxiways G, E and T including all civil, AGL and electrical works.

Construction of a new 3,000lm length storm drainage line with culverts and crossings.

Extension of existing cargo apron with complete AGL / electrical, mechanical and fuel hydrant system.

Relocation of the airport's main fuel supply line (approximately 11,500lm of 24" fuel lines with 350lm of 12" and 16" branches).

Replacing the airport's existing airfield lighting "control system" with a complete new "Control & Monitoring System" (ALCMS).